Repudiation Affirmation Trap
How "Wait and See" Can Wipe Out Your Damages Claim
- Adjunct Prof. Dr. Arun Kasi
If
the innocent party elects to affirm a contract following repudiation, they must
remain ready to perform. The burden of proof is high: emphasised by Teare J in Flame
v Glory Wealth Shipping [2013] EWHC 3153 (Comm), the innocent party must
show that, “but for” the repudiation, they would have been able to perform. A
failure to strategise correctly can be fatal to a claim in damages. In Olam
v Holbud [2025] EWHC 3187 (Comm), a buyer lost its award of €4.8 million in
damages for repudiation by the seller because the buyer redeployed its vessel
while affirming and prolonging contract after the seller’s repudiation.
Delivery Obligation and
Repudiation
In a commodity sale and purchase contract,
where time is frequently of the essence, the seller must be ready to deliver
and the buyer ready to take delivery of the cargo within the agreed time or
delivery window.
If one party tells the other, in clear and
unequivocal terms, that it will not deliver the cargo on the agreed date, ahead
of the delivery date, that amounts to an anticipatory repudiatory breach.
Similarly, if the party fails to deliver on the agreed date, that is an actual
repudiatory breach.
In either situation, the innocent party
has two options. One is to accept the repudiatory breach, thereby
bringing the contract to an end at that time, and immediately claim damages.
Another is to affirm the contract, thereby keeping the contract alive,
and insist on performance.
If the innocent party makes the second
election, it may terminate the contract by giving notice to that effect at a
later stage—in the case of anticipatory repudiatory breach affirmed by the
innocent party, it may wait and terminate for actual breach once the
contractual delivery date has passed without performance. Any claim for damages
will be subject to the innocent party’s duty to mitigate the loss.
Burden
on Innocent Party to Prove Readiness to Perform
If the innocent party elects to affirm the
contract, it must be ready to take delivery on the agreed time or delivery
window. If it is not, it may itself be in breach; more importantly, it will be
unable to claim substantial compensation for the breach of the other.
The burden of proof on the innocent
party claiming substantial damages is high. The innocent party must prove that,
“but for” the repudiation, it would have been able to perform their
contractual obligations, as emphasised by Teare J in Flame SA v Glory
Wealth Shipping Pte Ltd [2013] EWHC 3153 (Comm).
It is a strategic decision for an
innocent party whether it will accept a repudiatory breach or affirm the
contract. A failure to correctly strategise the exercise of the option may
deprive the innocent party of the right to claim substantial damages. This is
starkly illustrated by the decision in Olam Global Agri Pte Ltd v Holbud
Ltd [2025] EWHC 3187 (Comm).
Olam v Holbud [2025]
EWHC 3187 (Comm)
Facts: The
parties entered into a FOB contract in November 2021 for the sale and purchase
of yellow corn under GAFTA Contract No. 49, with a delivery period of 1-15 March
2022. The buyer had to nominate the vessel and provide the ETA at least 8 days
before arrival at the load port. Upon nomination by the buyer, the seller had
the option of nominating a Black Sea port for loading either in Ukraine or
Romania.
On 24 February 2022, Ukraine announced the
commencement of a full-scale invasion by Russia, and the closure of all Black
Sea ports. On the same day, the buyer nominated the vessel, The Finder,
with an ETA of 6/7 March 2022. Strangely, two days later on 26 February 2022,
the seller nominated a Ukraine port for loading.
That was followed by a wrongful force
majeure notice from the seller on 2 March 2022. Immediately, the buyer rejected
the force majeure notice and insisted on performance by nominating a Romanian
load port. The seller refused, and the buyer maintained its objection, thereby
keeping the contract alive.
On 9 March 2022, the buyer wrote to the
seller that the buyer would “refrain from holding Sellers in repudiatory
breach until 21 days after the end of the delivery period, and potentially 14
days thereafter” to give a chance to the seller to deliver from Ukraine.
Before the 21-day period expired (on 4
April 2022), the buyer redeployed The Finder and sent her off from the
holding position on 16 March 2022. Thereafter, on 26 April 2022, the buyer
elected to terminate the contract for the repudiatory breach by the seller.
Arbitration and Appeal: The
buyer claimed compensation in arbitration and was awarded €4.8 million damages.
The seller appealed under s 69 of the Arbitration Act 1996.
It was agreed that the date of default was
26 April 2022. As the buyer was not in a position to take delivery on 26 April
2022, having redeployed the vessel on other work by then, even if the seller
was ready to deliver on that day, the buyer was entitled to no more than
nominal damages, following Flame v Glory Wealth Shipping. The
Court held so, and the buyer lost the €4.8 million award.
Had the buyer accepted the repudiatory
breach on 2 March or 9 March 2022, when The Finder was ready to load
within the agreed delivery window, they would have been entitled to substantial
damages.
Alternatively, when affirming the contract
on 9 March 2022, if they did not extend the life of the contract, the buyer
would have had the option of terminating the contract on 16 March 2022 before
sending off The Finder. This would have saved the buyer’s entitlement to
substantial damages as the vessel would have been ready to load until the
termination of the contract.
But, because the buyer adopted the wrong
strategy of keeping the contract alive for a longer period while sending off
the vessel, they lost the entitlement to substantial damages.
The buyer argued that the seller “waived”
the right to call for the buyer’s performance by their representation that they
would not perform the contract. But the argument failed as it was not raised
before the arbitral tribunal in the first place, nor was a finding made by the
tribunal on this point.
The buyer argued that they could have
substituted a vessel on the default date but for the seller’s unwillingness to
perform. Again, this failed as the contractual deadline for substitution was 5
March 2022, which was not extended.
By extending the life of the contract and
sending off the vessel after the substitution deadline had passed, the buyer walked
onto a bridge that was collapsing behind them.
Takeaway
for Practitioners
Olam v Holbud
serves as a stark warning against the “wait and see” approach often
adopted by innocent parties in the face of anticipatory repudiation.
- Preserve the Ability to Perform:
If you choose to keep a contract alive after a counterparty’s repudiation,
you must maintain your own readiness to perform. If you redeploy your
vessel or sell your cargo elsewhere before accepting the repudiation, you
risk reducing your damages claim to zero.
- Estoppel Must be Pleaded:
If you are redeploying assets because the other side told you they
wouldn’t perform, you must ensure this reliance is explicitly communicated
and, if necessary, pleaded and proved as waiver.
- Substitution Deadlines Matter:
A counterparty’s breach does not automatically suspend your own procedural
deadlines for vessel nomination or substitution – the time for
substitution is of the essence. Missing a deadline by a day can destroy your
ability to perform.
The judgment reinforces that in English
law, there are no “free passes” on damages. Even against a “bad
actor,” the innocent party must prove their loss.
COPYRIGHT: Dr. Arun Kasi, © 2025
PARALLEL PUBLICATION: This article is also published on 4-5 Gray’s Inn Square publications.
JURISDICTION: This article is based on English law. It may be relevant to other commonwealth jurisdictions including Malaysia.
DISCLAIMER: This material is provided free of charge on a full disclaimer of any liability. The contents are the opinion of the author, the correctness of which is not assured. The opinion of others may differ. Readers should not rely on the contents provided in this material but should seek legal advice specific to their context. If they rely on the contents provided in this material, they do so solely at their risk. All the images, if any, used in this material are purely illustrative only and have no connection with the subject.